Petropavlovsk Republic Day Stage Installation Project

Petropavlovsk / Kazakhstan

ABOUT THE PROJECT

This project covers the end-to-end installation of high-standard outdoor stage and broadcasting/event infrastructure to be used in official ceremonies and mass celebrations held in the city of Petropavlovsk. The system has been designed in a modular structure that is resistant to all weather conditions, quick to assemble and dismantle, and suitable for reuse in future city events.

Project Details

  • Project Year: 2026
  • Location: Petropavlovsk / Kazakhstan
  • Our Partner: Railways Systems KZ

WHAT WE DID

1. Stage and Aluminum Construction Installation

  • • Modular aluminum truss/construction stage structure measuring 14 × 10 × 7 meters with roof protection was installed.
  • • Main performance podium measuring 12 × 8 meters was positioned.
  • • The mechanical and modular structure with a total weight of 10,000 kg was securely fixed.


2. Video and Display Systems Integration

  • • 3-piece LED screen infrastructure with a total surface area of 116 m² was integrated into the stage.
  • • The assembly and signal distribution of the screen groups weighing a total of 2,500 kg were completed.


3. Professional Audio Infrastructure Integration

  • • Sound system with a total power of 59,000 Watts was installed.
  • • For optimal sound distribution across the venue, 12 Line Array main speakers, 4 Subwoofers, and 4 Stage Monitors for on-stage monitoring were positioned.
  • • 10 power amplifiers driving the system, a digital audio mixer, and wireless microphone systems were commissioned.


4. Lighting, Effects, and Control Systems

  • • Total of 67 professional lighting fixtures were mounted on the stage:
    • - 36 Moving Heads (Swivel Head)
    • - 12 Strobe Lights
    • - 18 LED Beam lights
  • • 1 fog generator was added for visual atmosphere.
  • • All lighting and effect equipment were programmed to be controlled from a single central lighting console.


5. Power Calculation and Site Preparation

  • • Total electrical load calculation of 120 kW was made for the simultaneous and uninterrupted operation of all systems, and the power distribution infrastructure was planned accordingly.


BRANDS USED

ledtao
itc
fondlites
epetruss